At last week’s Council meeting the draft budget for 2020/21 now includes an extra $540,000 to address the funding shortfall following the rejection of our Federal Grant application
Council confirm the re-development will continue unless the building industry is shutdown as a result of CoVid-19
Completed clearance of contents from the clubrooms (thank you to Rob, Sharon & Paul Kennedy, Lachlan & Deb Purser, Greg Pickford & Rob Vrevc for their assistance)
Temporary facilities (canteen, change rooms & toilets) expected to be installed before Easter