The project to re-surface the ground is on schedule.
The old turf has been removed and disposed of. The sub surface has been reviewed and found to require remedial work in one location.
This work will be undertaken this week and the surface checked for leveling to International Hockey Federation standard and then sealed.
The shock pad material has been delivered and will be laid in the week commencing November 21.
At this stage the project is on schedule and within cost provisions. Work is due for completion by the end of December.